Installing Corrective Service on the Frame
this task allows you to update the level of code on the frame after you have downloaded a corrective service. this procedure should be run after any of the following components are replaced:
1 bulk power regulator (bpr)
2 bulk power controller (bpc)
3 distributed converter assembly (dca)
1. to install a corrective service on a frame, you must be a member of either the system administrator role or the service representative role. refer to the ibm hardware management console for pseries installation and operations guide for information on these roles.
2. do not power off any of the components in the frame at any time during this installation procedure.
interruptions can leave the power subsystem, or one of the other components in the frame, in an unrecoverable state.
to install a corrective service, do the following:
1. if you have not installed the corrective fix from ftp or diskette onto this hmc, perform steps to receive frame corrective service on the hmc (as described in “frame (power subsystem) firmware update” on page 37). then go to step 4.
2. from the hmc interface, in the navigation area (left side of the panel), open the software maintenance folder.
3. in the contents area (right side of the panel), double-click the frame icon. the frame application opens in the contents area.
4. in the contents area, click install corrective service. the install corrective service window opens.
5. select the corrective service version, and select the frame where the service will be applied.
unless you are directed otherwise, select the highest version number for the most recent fix.
6. click install. the installation may take up to an hour, depending on the number of parts in the frame that require an update. when installation is complete, a window opens to indicate installation status.
if you have replaced a single frame part and are using this procedure to update it, this process normally takes only two to five minutes.
7. if the installation fails, click reason for failure.
a. if you are able to correct the problems(s), click cancel and go to step 6.
b. if you are given an src, perform the steps to service the src, then return to this procedure.
c. otherwise, contact the next level of support.
8. after the corrective service has been applied successfully, click cancel to return.